Manager: We (meaning you) need to do task A. How long will it take?

Me: Task A will take X days to do.

Manager: That seems awful long.

Me: How long do you think it should take?

Manager: It surely could not take any longer than Y days.

Me: Ok, it seems you have an answer to your question then.

Later:

Manager: It’s been Y days, why isn’t task A done yet?

  • markstos@lemmy.world
    link
    fedilink
    arrow-up
    1
    ·
    2 hours ago

    That pattern is also recommended in the book. Break down estimates into chunks of 5 hours or less.

    With lots of smaller tasks, estimates tend to both be more accurate due to smaller scope, and some of the over/under inaccuracies will cancel out.